In Jim Williams’ 8/13 Letter to the Editor about the Lexington High School (LHS) project, he identified that he led a “ten-citizen group”* in an appeal to the Massachusetts Department of Environmental Protection (MassDEP). As a result, construction has largely stopped. I replied to Mr. Williams’ letter with a full description of the financial and schedule impacts of the delay based on estimates presented at the Permanent Building Committee (PBC) meeting on 8/19. The presentation assessed the ever-growing impacts based on MassDEP’s decision date.

The design team is confident that MassDEP will allow the project to proceed (they have seen this tactic used before) – the question is how long will it take? At a walkthrough of the project on 8/27, the MassDEP representative said the fastest possible review is two weeks, but this is a large project and will take longer – potentially much longer, we do not know.

Briefly, here are the impacts:

  • September 1 decision: $1 to $2.5 million increased costs due to escalation, resequencing, schedule compression, premium time, and shifting more work into winter months. Students will still be in the new school in September 2029.
  • October 1 decision: $2.5 to $5 million increased costs. With hard work by Town staff and team and some luck, students may still be in classrooms in September 2029.
  • November 1 decision: $17.6 million increased costs. Students would move into the new school during winter break (at the earliest). Both buildings would need to operate in the meantime and additional furnishings and IT would have to be purchased (not reused). Field construction will be delayed by a year.

The proponents have clearly expressed their displeasure with the project. They now have the opportunity to save the town millions of dollars by rescinding their appeal. By stopping the appeal now, they will be able to walk away from this effort with their heads held high. Not only will they have clearly made their point to the community, but they will also save the town millions of dollars and help to ensure that our students enter a new high school that meets their educational needs as scheduled in September 2029. Please join me in encouraging the proponents to make this courageous move.

Todd Rhodes

*Petition signers: Alan Seferian, James Williams, Jean Williams, Catherine White, Douglas White, Shailesh Chandra, Shubhra Chandra, Cheryl King, Thomas King, Philip Cunningham, Marianne Mckenna, Olga Guttag.

Join the Conversation

2 Comments

  1. The appeal isn’t about the money, it’s about the wetlands and the fact that alternative options were never really considered. Those of us who know people on the SBC know that the plan was decided upon before all the ‘open meetings’ and feedback occurred. The SBC has assumed they will be able to roll through the environmental laws that the rest of us have to abide by- have you ever tried to get a permit for construction in Lexington if you live near a wetland? So far they have been able to, but they should have seen this petition coming.

    1. This has become a very old and very tired story. “Things didn’t go my way, so that means alternatives were not considered.” The fact is, in the more than two years of public meetings about the new high school, alternatives were considered. There are never any perfect solutions to any project. The School Building Committee sifted through the alternatives and made the choice that was best for the new high school, best for the town, and most importantly, was in the best interest of the students who will be attending the new high school. It is time to move on from this lost cause and get on with the business of building the new Bloom design high school.

Leave a comment
Commenters must be registered and logged in with a verified email address and REAL FIRST AND LAST NAME. To register for an account visit the registration page for our site. If you already have an account, you can login here or by clicking "My Account" on the upper right hand corner of any page on the site, right above the search icon.

Commenters must use their real first and last name and a real email address.
We do not allow profanity, racism, or misinformation.
We expect civility and good-faith engagement.

We cannot always fact check every comment, verify every name, or debate the finer points of what constitutes civility. We reserve the right to remove any comment we deem inappropriate, and we ask for your patience and understanding if something slips through that may violate our terms.

We are open to a wide range of opinions and perspectives. Criticism and debate are fundamental to community – but so is respect and honesty. Thank you.